Civil Technology Woodworking Memo 1 (English)

May-June 2022 โ€” Grade 12 / Matric โ€” Civil Technology

Memo 2022 Grade 12 English
โ†“ Download PDF Facebook X ๐Ÿ“„ 434 KB View Exam Paper
Preparing document

๐Ÿ“‹ Document Analysis

๐ŸŽฏ 200 marks ๐Ÿ“„ 7 pages ๐Ÿ“ 67 items found ๐Ÿ“š 2 topics
See full analysis

Questions โ€” A Preview of What to Expect in the Document

67
This section provides a quick preview of questions from the document. It may not display every question or the complete wording of each one. For the full content, including diagrams, tables and other information, view the original PDF above.
Q1โ€” Section header โ€”
1.1.1Thermo pl astic/Thermo plastic powder coating (1\
1.1.2Electroplating (1\
1.1.3Curing (1\
1.1.4Paint/Varnish (1\
1.1.5Galvanising (1\
1.2.1Non skid material should be fitted to: Prevent ladders from moving when worke rs are using them Ensure stability of the ladder when in use ANY ONE OF THE ABOVE (1\
1.2.2Wooden ladders are better: To prevent electrical shock Because it is a poor conductor of electricity ANY ONE OF THE ABOVE (1\
1.2.3Aluminium ladder is: Lighter More durable Easier to handle Easy to clean Stronger Suitable to extend to
1.2.4Wooden ladders can be treated with: Linseed Oil/Oil Clear varnish/Varnish Wood prese rvative/Preservative ANY TWO OF THE ABOVE (2\
1.3The scaffold platform: Must have guard rails Must have toe boards Should have sufficient room between the structure and the platform for the worker to sit and work Must be free of any obstructio n/waste/projecting nails/equipment that can
1.4A safety net can be erected: Above an entrance At passageways At areas wher e persons work while work is being performed above them To prevent falling objects from injuring workers ANY TWO OF THE ABOVE
1.5.1Rawlbolt/Expansion bolt/Anchor bolt (1\
1.5.2Drill hole Remove debris/Clean the hole Remove the bolt and washer/insert the shield (3\
1.6Dumpy level d etermine Levels and heights Differences between levels and vertical heights Levels and slopes Distances ANY ONE OF THE ABOVE
Q2โ€” Section header โ€”
Q3โ€” Section header โ€”
3.1.1Bolted (1\
3.1.2bolt (1\
3.1.37 metr 1\
3.1.450 mm x 76 mm (1\
3.1.5
3.5.1No wall plate ill not be able to tie/fasten the after to the wall plate
3.5.2NOTE: IF A LINE DIAGRAM WAS DRAWN ONE MARK WILL BE ALLOCATED FOR THE SLOPE ASSESSMENT CRITERIA MARK Wall p late Rafter
Q4โ€” Section header โ€”
4.1.1(1\
4.1.2(1\
4.1.3(1\
4.1.4(1\
4.1.5(1\
4.1.6(1\
4.1.7(1\
4.1.8(1\
4.2600 mm (1\
4.3afety factors before excavations begin competent person
4.4Steel shuttering Sturdy enough to bear the mass of wet concrete without collapsing Stronger than wood and timber board products Easy to remove when concrete has set Not as
4.5Levelling a site: Filling a slope Cutting away a slope Cutting and filling Excavated soil can be used ANY THREE OF THE ABOVE (3\
4.6Components of shuttering Folding wedges/ edges alling boards
4.7lock board is Lightweight as y to work wit h, using ordinary woodwork tools
4.8.1Tamping rammer 4. .2 Safe handling
Q5โ€” Section header โ€”
5.1Wet the wall (1\
5.2Water will make the mixture workable
5.31:3 (cement sand\ (1\
5.4Splatter dash finish platter finish (1\
5.5Types of screeds Dry scree Monolithic screed
5.6Water reducing agent (1\
5.7.1The cavity will nsure that no wate r will penetrate the inner wall rovide insulation against heat/sound/cold (2\
5.7.2OR NYLON WALL TIE TWISTED PATTERN WALL TIE ASSESSMENT CRITERIA MARK Correctness of drawing: ASSESSMENT CRITERIA MARK
5.8Plaster sand River sand/Dune sand/ Sand/ Cement slurry (1\
5.9Construction failure: Poorly constructed edge restraint Haunching not correctly done ANY ONE OF THE ABOVE Civil T echnology: Construction
Q6โ€” Section header โ€”
6.1.1(1\
6.1.2(1\
6.1.3(1\
6.1.4(1\
6.1.5(1\
6.2Installation of driven in situ piles: Metal pipes that contain a dry concrete mi x (gravel plug\are driven into drilled hole in the ground
6.3.1Hollow core con crete block/Concrete block /Block
6.3Purpose of B is: Used for the placement of conduit pipes Serves as insulation Reduce the weight Lower the cost of materials ANY ONE OF THE ABOVE
6.3Disadvantages: echanical handling is required on site Manual lab our is required to place blocks (2\
6.3Components for rib and block floor: Steel mat/Mesh/Steel/Reinforcement In
6.46. .1 Anchor bar /Pressure bar/Compression bar
6.4ASSESSMENT CRITERIA MARK Correctness of drawing: Shear bar Minimum concrete cover depth indicat
6.6Elements to p rotect reinforcing from Water that is moderately aggressive Co
6.7.1
6.7.2 Skirting: Internal dimensions of long walls = 8 500 mm

Multiple Choice Options

1
C)Le

Topics Identified

2
MaterialsConstruction

Mark Allocation

Total200 marks
Sections20 + 40 + 30 + 40 = 130 marks

Paper information

SubjectCivil Technology
Year2022
SessionMay-June
TypeMemo
PaperPaper 1
LanguageEnglish
Pages17
Downloads10

Examination context

Decade2020s
Years ago4y
Seasonโ€”
Start dayโ€”
Exam periodโ€”
Days since examโ€”

About Civil Technology examination preparation

This Grade 12 examination resource can be used as part of a structured revision programme. Past papers are most useful when learners attempt questions independently, work within a realistic time limit, and review their answers afterwards.

How to use this resource for revision

A past examination paper is most useful when it is treated as an active revision exercise. Try the questions yourself before checking the corresponding memorandum. Where you make an error, identify the reason โ€” was it a knowledge gap, a calculation mistake, an interpretation issue, or an examination technique problem?

For stronger examination practice, complete the paper without unnecessary interruptions and keep track of the questions that take the most time. Afterwards, review the memorandum and separate knowledge gaps from mistakes caused by interpretation, calculation, structure, or examination technique.

understanding question requirements
applying subject knowledge
working under time constraints
checking answers
identifying revision priorities

A practical revision approach

Start by completing the resource without looking at the memorandum. Review incorrect and incomplete answers afterwards and make a short revision list based on the areas that caused difficulty.

Grade 12 subject hubs

Each matric subject has its own dedicated hub on Freemode with every past paper and marking memorandum we have archived for that subject.

Corresponding examination paper

Examination paper available

Open the corresponding examination paper to practise the questions before reviewing the marking memorandum on this page. Attempt every question under timed conditions for the most realistic preparation.

Civil Technology Civil Services Paper 1 (English) โ†’

File details

File size434 KB
Pages17
Archived on11 October 2026
File age12d
ContributorFreeMode
FingerprintA0BDFD904043

Questions and learner discussion

Log in to ask a question or leave a review.

No questions or discussions have been posted yet.